top of page
Genoa Pavement Rehabilitation

SALIENT FEATURES

  • Field Investigations

  • Data Analysis

  • Plans & Specifications

  • Cost Estimate

  • Construction Support

  • Construction Cost: $9.5M+

  • infraTECH served as Prime consultant

CLIENT

Harris County

LOCATION:

Houston, Texas

BACKGROUND

Every year Harris County spends millions of dollars to rehabilitate existing pavements to improve rideability. These county roads include local roads in residential areas, minor collectors, and multi-lane arterials- both asphalt and concrete pavements. Rehabilitation options for asphalt pavements include mill and overlay, base repair, replace existing pavement, and replace existing asphalt pavement with concrete pavements. For existing concrete pavements, rehabilitation options include panel replacement and reconstruction.

PROJECT FEATURE

The Genoa pavement rehabilitation project consists of a total of 38 streets in the Genoa area. The total length of project sections is approximately 22.0 miles that includes local roads in residential areas, minor collectors, and multi-lane arterials consist of both asphalt and concrete pavements. Out of the 36 asphalt pavements addressed, 14 received full-depth repairs and 22 received only mill and overlay treatments. For concrete pavements, distressed panels were identified and replaced.

RELEVANT SERVICES

As the prime consultant, infraTECH was responsible for project management, developing plans, specifications, and estimates (PS&E) and support during bidding and construction for this project.